Generator Sizing Guide Africa
Learn how to estimate generator capacity using load demand, starting current, phase, duty and runtime.
How to Size a Generator Correctly
Correct generator sizing is one of the most important steps when planning a backup or independent power system.
A generator that is too small may struggle with starting loads, voltage stability and overheating. A generator that is unnecessarily large can increase purchase cost, fuel consumption and maintenance requirements.
Start by reviewing the equipment that must operate during an outage or at the project site.
Step 1: Prepare a Load List
List every appliance, machine or system that will run from the generator.
- Lighting
- Refrigeration
- Air conditioning
- Pumps
- Compressors
- Computers and office equipment
- Workshop machinery
- Medical equipment
- Industrial motors
Step 2: Calculate Running Load
Add the normal running demand of the equipment expected to operate at the same time.
The final generator should not be selected only from the total nameplate watts because motor starting loads can temporarily require much more power.
Step 3: Identify Starting Loads
Pumps, compressors, air conditioners and electric motors can draw substantially more current during startup than during normal operation.
This starting requirement must be included when selecting generator capacity.
kW and kVA
Generator capacity may be expressed in kilowatts (kW) or kilovolt-amperes (kVA). The relationship depends on power factor.
For larger commercial and industrial applications, professional load assessment is recommended rather than relying on a simple conversion alone.
Single Phase or Three Phase?
Confirm the electrical system before ordering.
Browse single-phase generators or three-phase generators according to the site requirement.
Standby vs Prime Duty
Standby equipment is generally selected for outage backup, while prime-rated equipment may operate for extended periods where grid supply is limited or absent.
Allow for Future Expansion
If additional equipment is likely to be added, allow reasonable capacity for future loads without grossly oversizing the generator.
Generator Selection Checklist
- Total running load
- Largest starting load
- Voltage
- Frequency
- Phase
- Expected runtime
- Duty classification
- Noise requirements
- Installation environment
- Future expansion
Continue Your Research
Browse Diesel Generators Africa, the main Generator Solutions page and the diesel generator catalogue.
Manufacturer References
Current manufacturer documentation from Cummins and Perkins can help confirm model-specific ratings and duty classifications.
Need Help Sizing?
Send your equipment list and project details and we can use them to help narrow the generator options.